11/ 2/72—Answer of the Dept. of Justice to applicant's objections to to document requests & motion for protective orders.

12/13/72-Application for issuance of subpoenas duces tecum.

1/8/73-Answer of the Dept. of Justice to applicant's motion for order modifying procedural schedule.

2/12/73-Request for admissions & interrogatories as to proposed con

tentions.

3/ 2/73-First response of the Dept. of Justice to applicant's interrogatories.
3/ 2/73-Answer to applicant's motion to extend time to object to request
for admissions & motion to compel applicant's response.
3/22/73-Reply of the Dept. of Justice to applicant's answer to motion to
compel response.
4/2/73-Supplemental response of the Dept. of Justice to applicant's
4/17/73-Answer of the Dept. of Justice to applicant's motion to compel
production of documents & motions of the dept. for protective
orders & to compel production of documents by applicant.
6/28/73-Notice of appearance; Answer of the Dept. of Justice to applicant's
motion for leave to submit outside experts' direct testimony in
written form

interrogatories.

7/12/73-Answer of the Dept. of Justice to intervenors' motions for reconsideration & to compel.

8/10/73-Motion to the Board for an order requiring applicant to state the facts expected to be proved by its outstanding requests to nonparties.

8/22/73-Further request for admissions & Interrogatories.

9/6/73-Dept. of Justice petition to the Board for order establishing a Michigan location for hearing for taking testimony of Michigan witnesses.

9/20/73-Motion to compel production of Michigan Pool Committee

minutes.

10/15/73-Motion of the Dept. of Justice to compel discovery regarding certain computer material.

10/15/73-Brief of the Dept. of Justice to assist Board in determining impact Commission's memorandum & order (Docket 50–382A) upon this proceeding.

10/8/74-Brief & proposed findings of fact of the U.S. Dept. of Justice. Duke Power Company (Docket Nos. 50-269A, 50-270A, 50–287A, 50–369A, 50-730A):

9/5/72-First joint request of Dept. of Justice, AEC Regulatory Staff & Intervenors for production of documents by applicant for period since 1/1/60.

10/25/72-Answer of the Dept. of Justice to applicant's objections to document requests & motion for protective orders.

11/16/72-Application for issuance of subpoenas duces tecum. 12/20/72-Answers of the Dept. of Justice to motions of Virginia Electric & Power Company, Carolina Power & Light Company, & South Carolina Electric & Gas Company.

2/2/73-New proposed list of subissues of fact submitted by the Dept. of
Justice.

2/8/73-Affidavit of Wallace Edward Brard in support of motion for
reconsideration of Board's order of 1/8/73.
2/26/73-Reply brief of the Dept. of Justice on relationship between AEC's
proceeding under Sec. 105 of the Atomic Energy Act & FPC's
proceeding under Sec. 205 of the Federal Power Act; with
Dept's proposed issues of fact to be inserted under Board's
subissues b. 1-4.

3/30/73-Revised interrogatory of the Dept. of Justice concerning ap-
plicant's filing system.

4/23/73-Answer of the Dept. of Justice to motion of VEPCO to quash or to limit subpoena duces tecum.

6/ 6/73-Answer of the Dept. of Justice to applicant's motion to amend par. G of prehearing order #6 & separate motion of the Dept. to amend par. G of prehearing order #6.

7/30/73-Answer of the Dept. of Justice to applicant's motion to amend prehearing order #2.

7/31/73 Answer of the Dept. of Justice to applicant's motion for protective orders.

9/17/73-Interrogatories & document request of joint discoverers & motion to compel response.

9/28/73-Request of the U.S. Dept. of Justice for additional time to reply to interrogatories & document production request of applicant. 10/ 3/73-Answers of joint discoverers to applicant's motion for protective order concerning commencement of depositions.

10/11/73-Answers of the Dept. of Justice to applicant's motion to stay depositions & request for expeditious ruling on that motion. 10/18/73-Answer of Dept. of Justice to applicant's motion to determine procedure for review of attorney-client privilege claims. 10/23/73-Brief of the Dept. of Justice to assist Board in determing impact of Commission's memorandum & order (Docket 50-382A) upon this proceeding.

11/8/73-Request of the U.S. Dept. of Justice for additional time to reply to interrogatories & document production request of applicant. 11/19/73-Memorandum of Dept. of Justice on the scope & application of attorney-client privilege. 11/28/73-Request of the U.S. Dept. of Justice for additional time to reply to interrogatories & document production request of applicant. 11/30/73-Answers of the Dept. of Justice to interrogatories of the applicant. 12/7/73-Supplemental memorandum of Dept. of Justice on attorney-client

privilege.

12/20/73-Joint motion of all parties for a modification of the prehearing

schedule.

1/4/74-Answer of the Dept. of Justice to applicant's motion for a protective order.

1/10/74 Supplementary answers of the Dept. of Justice to interrogatories of the applicant.

1/22/74-Answer of the Dept. of Justice to applicant's motion to compel. 1/28/74-Answers of the Dept. of Justice to applicant's motion for leave to reply.

2/7/74 Joint motion of all parties requesting changes in the schedule of the proceeding.

3/ 7/74-Fourth response of the Dept. of Justice to applicant's interroga

tories.

5/13/74-Answer of the Dept. of Justice to intervenors' motion for extension

of time.

5/14/74-Motion of the AEC Staff & the Dept. of Justice to amend licenses for Oconee Units 1, 2 & 3 & McGuire Units 1 & 2 by attaching license conditions.

No date Joint recital of contested issues of fact & law. Duke Power Company (Docket Nos. 50-413A & 50-414A):

9/12/73-Answer of Dept. of Justice to applicant's objection to consolidation & motion to determine issues for hearing.

5/10/74-Response of the Dept. of Justice to questions posed in board's 4/25/74, notice of hearing & notice for special prehearing conference.

5/23/74-Motion of the Dept. of Justice to limit participation; answer to applicant's motion for full implementation of settlement; advice to Board concerning issues appropriate for hearing. Georgia Power Company (Docket No. 50-366):

9/25/72-Motion to consolidate of the Dept. of Justice.

12/19/72-Supplemental statement of common issues in support of the Dept. of Justice's motion to consolidate.

1/ 3/73-Notice of appearance.

1/16/73-Statement of the Dept. of Justide with regard to legal theory & supporting facts.

4/ 5/73-Response of the Dept. of Justice to Georgia Power Company's Second recital of contested issues.

5/31/73-Second Joint request of the Dept. of Justice, AEC Regulatory Staff, & intervenors for production of documents by the applicant.

6/14/73-Motion of the parties for an extension of time.

6/15/73-Report of the Dept. of Justice & AEC Regulatory Staff.

7/25/73-Answer of the joint discoverers to applicant's objections to the first joint request for the production of documents.

8/29/73-Answer of the joint discoverers to applicant's objections to the second joint request of the Dept. of Justice, AEC Regulatory Staff, & intervenors for production of documents by the applicant.

9/4/73-Answer of the joint discoverers to applicant's objections to the substitute questions for the second joint request for the production of documents by applicant.

10/12/73-Proposed schedule of the Dept. of Justice & AEC Regulatory

Staff.

11/5/73-Report of the Dept. of Justice & AEC Regulatory Staff.
11/16/73-Joint discoverers' amendments to their second joint discovery
request of the applicant & joint discoverers' amended motion to
compel discovery of the applicant.

12/ 4/73-Report of the Dept. of Justice & AEC Regulatory Staff.
12/21/73-Motion of the parties for a postponement of procedural dates.
No date-Recital of contested issues of law & fact.

Louisiana Power & Light Co. (Docket No. 50-382A):

No date-Affidavit of Wallace Brand.

11/8/72-Statement of the Dept. of Justice concerning matters contained in Louisiana Power & Light Co.'s "motion for expeditious denial" filed 10/30/72.

2/23/73-Memorandum & Order.
3/21/73-Notice of appearance.
3/22/73-Notice of appearance.

3/29/73-Request for extension of time.

4/ 2/73-Answer of AEC Regulatory Staff to Louisiana Power & Light
Company's answer to Commission's notice of antitrust hearing
on application for construction permit for related motions.
4/ 3/73-Notice of receipt of supplemental antitrust advice from Dept.
of Justice.

4/4/73-Order granting request of U.S. Dept. of Justice for additional
time to reply to answer to notice of antitrust hearing on
application for construction permit & related motions.
4/ 5/73-Reply & answer to Dept. of Justice to applicant's papers of
3/20/73.

4/6/73-Notice of appearance.
4/9/73-Answer of Cities of Lafayette & Plaquemine, Louisiana, to answer
of Louisiana Power & Light Co. filed 3/20/73 & related motions.
4/ 9/73-Motion of the Dow Chemical Company for leave to file a reply
to applicant's answer to notice of antitrust hearing on appli-
cation for construction permit & related motions.

4/24/73-Memorandum & opinion of Board with respect to petitions to
intervene in an antitrust hearing relating to application for
construction permit.

4/27/73-Notice of Dept. of Justice advice.

5/ 4/73-Motion of the Dow Chemical Co. for leave to amend & supplement
its petition for leave to intervene & request for hearing.
10/30/73-Answer of Dept. of Justice to motion of applicant for clarification
of the Commission's order of 9/28/73.

11/12/73-Memorandum of the Dept. of Justice pursuant to notice & order
of 10/30/73.

2/8/74-First joint request for the production of documents by application.

7/18/74-Dept. of Justice reply to applicant's motion that the AEC or The Atomic Safety & Licensing & Appeal Board direct certification of the record for appeal.

9/5/74-Post-show-cause-hearing brief of the Dept. of Justice.

11/13/74-Motion to modify board's memorandum with respect to appro

priate license conditions.

12/6/74-Brief of Dept. of Justice on appeal from initial decision of hearing

board.

Pacific Gas & Electric Company (Docket Nos. 50-358 & 50–359):

9/7/72-Notice of appearance by the Dept. of Justice.
9/20/72-Notice of appearance.

The Toledo Edison Company, The Cleveland Electric Illuminating Company (Docket No. 50-346A); The Cleveland Electric Illuminating Company, et al. (Docket Nos. 50-440A & 50-441A):

1/24/74-Notice of appearance by the Dept. of Justice.
6/19/74-Proposed expedited hearing schedule.

7/12/74-Response of Dept. of Justice to order requesting clarification.
7/15/74-Expedited hearing schedule proposed by the Dept. of Justice.
8/29/74-Notice of appearance by the Dept. of Justice
9/9/74-Motion by the Dept. of Justice for a protective order.

10/10/74-Response by the Dept. of Justice to applicant's motion for summary disposition

11/27/74-Response of Dept. of Justice to applicant's first request for production of documents & answers to interrogatories.

12/9/74-Motion by Dept. of Justice to compel discovery & to revise time schedule to take into account applicant's noncompliance. 12/12/74-Motion by the Dept. of Justice to quash or modify applicant's subpoena & to enforce the sequence & timing of discovery ordered by the licensing board.

1/ 2/75-Memorandum of the Dept. of Justice in documents production submitted at the request of The Atomic Safety & Licensing Board.

1/7/75-Reply memorandum of the Dept. of Justice on document dis

covery.

2/14/75 Supplemental interrogatories by the Dept. of Justice to The
Cleveland Electric Illuminating Company, Ohio Edison
Company, Pennsylvania Power Company & the Toledo Edison
Company.

2/18/75-Dept. of Justice proposed transcript corrections.

B. HOLDING COMPANY ACQUISITIONS (SEC)

American Electric Power Co., Inc. (SEC Adm. Proc. File No. 3-1476) 3/17/69-Application of the U.S. Dept. of Justice for leave to submit an amicus statement.

11/12/69-Response to American Electric Power Company, Inc.'s motion to quash subpoena dated 11/3/69.

3/13/70-Reply of Division of Corporate Regulation & Dept. of Justice to petition for review by American Electric Power Company, Inc. ("AEP") of Examiner's Ruling denying AEP motion to terminate cross-examination.

4/24/70-Application for order requiring production of books, papers &

documents.

10/19/70-Response to Dept. of Justice to AEP's application of 10/9/70.
11/6/70-Statement of the Dept. of Justice with respect to the application
for review of the Division of corporate regulation.

2/19/71-Dept. of Justice motion for reconsideration of orders requiring
production of documents.

2/8/72-Response of the Dept. of Justice to AEP's application for review, dated 1/28/72.

4/11/72-Letter.

6/6/72-Answer to Dept. of Justice & Division of Corporate Regulation to application by AEP for interlocutory review of Examiner's order denying motion to omit initial decision.

9/18/72-Brief & proposed findings of fact of the U.S. Dept. of Justice. 10/24/72-Reply Brief of the U.S. Dept. of Justice.

4/ 9/74-Brief of the U.S. Dept. of Justice.

New England Electric System, et al. (SEC Adm. Proc. File No. 3–1698). 6/1/71-Brief of the U.S. Dept. of Justice.

1/29/73-Reply Brief on exceptions of the Dept. of Justice.

C. RESTRICTIVE PRACTICES (FPC)

Docket No. R.345 (competitive bids in procurement): See, VI. NATURAL GAS (FPC) (Restrictive Practices).

VI. NATURAL GAS (FPC)

A. MERGERS AND ACQUISITIONS

American Natural 50% acq. of Great Lakes Transmission Company (Docket No.s CP 66-110 et al.):

11/ 3/69-Brief of Dept. of Justice on remand.

12/ 5/69-Reply of Dept. of Justice to initial brief & motion of Michigan Wisconsin Pipe Line Company & Michigan Consolidated Gas Company.

2/6/70-Exceptions of the Dept. of Justice to Examiner's initial decision on remand.

8/10/70-Application of the Dept. of Justice for rehearing of opinion No. 580 & accompanying order.

B. RATES

C. PIPELINE CERTIFICATES & PERMITS

Great Lakes Transmission Company (Docket Nos. CP 70-19, CP 70-20); Michigan Wisconsin Pipeline Company (Docket Nos. CP 70-21, CP 70-22); Midwestern Gas Transmission Company (Docket Nos. CP 70-23, CP 70-24) (pipe line interconnection with Great Lakes):

12/16/69-Petition of Dept. of Justice for leave to File a statement of posi

tion.

Northwest Pipeline Corporation (Docket Nos. CP 73-331; CP 73-332; CP 73-333):

8/21/73-Joinder in motion for expedited proceedings.

10/23/73-Application of intervenors Arizona Public Service Company, Tucson Gas & Electric Company for rehearing of Commission order issued without public hearing.

D. RESTRICTIVE PRACTICES

Docket No. R.345 (competitive bids in procurement):
3/17/69-Comments of the U.S. Dept. of Justice.

VII. BANKING AND FINANCE (FRB, FDIC, COMPTROLLER, FHLLB)

A. BANK MERGERS & ACQUISITIONS

Alabama Bancorporation:

3/19/73—Memorandum of the U.S. Dept. of Justice on the competitive effects of the captioned applications.

American Fletcher Corp. (acq. voting shares of Southwest S & L Assoc): 11/30/73-Comments of the Dept. of Justice.

Trust Co. of Georgia (acq. of Peachtree Bank & Trust, Chamblee, Ga.): 3/ 2/71-Petition for reconsideration of order approving application for acquisition of assets & assumption of liabilities under Bank Merger Act.

B. BANK HOLDING COMPANY DIVERSIFICATION

Armored Car or Courier Services:

5/11/72 Comments of the U.S. Dept. of Justice.

Factors, acquisition of:

12/10/71-Petition for acceptance of late comments. Finance Companies, Small, acq. of:

12/ 1/72 Memorandum of the U.S. Dept. of Justice.

Investment advisors to investment companies: •

9/24/71-Comments of the U.S. Dept. of Justice.

Mortgage Companies, acq. of:

12/3/71-Petition for acceptance of late comments. Nonbanking activities, generally:

2/26/71—Memorandum of the U.S. Dept. of Justice.

« AnteriorContinuar »